Wednesday 5 July 2017

Burford Boarding School


As the work commences we have mission on!
The works have started at Burford Boarding School to completely refurbish the washrooms.

Work started on Monday 3rd July to remove the old washroom furniture, over the course of 8 weeks these washrooms will be transformed into modern washrooms.

This week sees the removal of the old furniture.
The drainage and new walls come into place, within the second week.
Commencing the 17th July the walls will be completed and Saniclad panels are installed, the first fix for plumbing and electrics will take place.

Flooring and cubicle installations will follow along with a suspended ceiling and external drainage with the second fix for plumbing and electrics.
The final week will see the clean down and handover take place in time for the start of the new academic year.

I can't wait to see how this develops and the finished result.
I'm intrigued to know the colour scheme that the school has chosen too?

What would your colour choice be if it were your school?